Securing Fiber Access to a Thai Data Center

A carrier’s confirmation that fiber runs close to a proposed data center is encouraging. The distance looks manageable, and the developer starts planning around a connection. Getting from that network to the facility, however, might involve a highway crossing, space in a duct or on utility poles, and access across someone else’s land.

Those arrangements affect when the facility opens and what it promises customers. A coverage map shows where the network runs, but does not establish which permissions and access arrangements support the proposed connection.

The carrier’s role shapes the access question

Section 39 of Thailand’s Telecommunications Business Act requires a licensee seeking to exercise statutory installation rights to submit a route plan for regulatory approval before proceeding. It treats existing infrastructure, state public-domain land and private land differently. [1]

The National Broadcasting and Telecommunications Commission (NBTC) identifies network-owning Type 2 and Type 3 licensees as eligible applicants in its published procedure. For a developer buying connectivity, the question is who will secure the route and which rights that operator holds. [3] Our Type 1 licensing guide explains how service resellers without their own network are licensed.

The carrier selling the service might rely on a wholesale network owner or another infrastructure provider for part of the connection. If installation stalls, resolving it may require action by a party outside the customer’s contract. The developer’s opening timetable then rests partly on a relationship it does not control.

The route crosses several approval processes

The NBTC’s 2017 rights-of-way notification requires route and equipment details and addresses the interests of other operators, authorities, utilities and landholders. Operators must also submit changes to an approved plan for approval before carrying them out. A revised route brings further regulatory work. [2]

The road determines which authority the carrier deals with. Section 48 of the Highway Act requires prior written permission from the highway director or a delegate for poles, cables, ducts and other works within a highway boundary. Section 56 sets a separate regime for special highways. The Department of Highways publishes a utility-works procedure within its jurisdiction; rural and local highways involve the Department of Rural Roads or the relevant local authority. Telecommunications approval sits alongside those road requirements. [5, 8]

Closer to the facility, the connection might cross an estate road, shared entrance or building controlled by another party. The route drawing shows one continuous line, but different arrangements support each segment. The property documents and contracts establish how far those arrangements reach. Our discussion of overlapping data-center regulation places these separate approvals in their wider context.

Existing ducts and poles do not guarantee available space

An existing duct offers an alternative to new excavation, provided it has usable space along the required section. The NBTC’s 2017 guidelines on the use, investment and construction of communications ducts include rules on access between licensees, capacity information, negotiations and fair, reasonable and non-discriminatory terms. They also recognize insufficient capacity caused by engineering constraints. [2, 4]

A carrier might show a duct on its route plan while it is still checking capacity, confirming entry and exit points or negotiating access. The infrastructure exists, but the carrier has yet to establish whether it can use it for the proposed connection.

Utility poles present similar constraints. Under its 2023 regulations, the Provincial Electricity Authority (PEA) requires written permission before installation and assesses pole capacity and structural safety. Licensed telecommunications operators ordinarily need NBTC layout approval before applying to PEA, which adds a sequence to the approvals. [6] The Metropolitan Electricity Authority (MEA) has its own 2023 regulation and reserves discretion over permission in areas designated for moving overhead electricity cables underground. [9]

PEA’s enforcement activity shows why existing cables offer limited reassurance. In January 2025, it reported removing unauthorized communications cables along the Rangsit–Pathum Thani road. PEA said the poles could not support large volumes of cables and it could not permit further attachments. Cables beside a site do not establish that a new connection has authorized space. [7]

The carrier needs access to keep the connection working

After opening, the facility needs the carrier to reach and repair faults. Section 42 of the Telecommunications Business Act requires written notice to the land’s possessor at least 30 days before ordinary entry for inspection, maintenance and repair. It permits immediate entry where damage must be repaired urgently. The rights-of-way notification also addresses routine maintenance notice and emergency access. [1, 2]

A commitment to restore service within hours needs access arrangements to support it. Technicians might need a utility’s cooperation or entry through estate or building security. The statutory notice period alone does not settle how quickly the carrier can enter under its agreements or whether a particular failure qualifies for emergency entry.

Road works or infrastructure reorganization can require relocation and cause extra costs or interruptions over the facility’s life. The applicable rules, permissions and contracts shape who bears those consequences. Arrangements made for the initial installation sometimes leave that later work unresolved.

Two carriers can still share a vulnerable stretch of the route. If both use the same duct beneath a road, damage there could interrupt both services. Otherwise separate connections might also converge at the facility’s entrance.

That matters when a customer expects its second connection to survive a failure of the first. The commercial position turns on the actual routes and the parties’ commitments about diversity, rather than the number of suppliers.

Unresolved access issues affect customer commitments

A proposed delivery date sometimes assumes that third-party permissions, construction access and capacity arrangements will fall into place. Once the developer commits to accepting customers, a connection delay reaches beyond the carrier’s installation work into the facility’s own obligations. Our analysis of the limits of existing approvalsexplores the distinction between permission to conduct a business and authority to develop and operate a particular facility.

Thai law offers mechanisms for addressing certain access obstacles, subject to the relevant conditions and facts. Their existence does not establish when a disputed route will become available. A timetable that assumes regulatory intervention will resolve an access problem still carries uncertainty. [1, 2]

Fiber access belongs in the wider assessment of the site and its operating model. Following the route from the carrier’s network into the facility reveals where delivery still requires another party’s permission, space or cooperation. Those arrangements shape both the opening date and the service the facility will provide afterward.


Disclaimer

This article provides general information as of 25 November 2026 and does not constitute legal advice. Laws, regulations and regulatory practice may change, and their application depends on the facts and arrangements of each project. Readers should obtain advice on their specific circumstances before acting on or relying on this article. Reading this article does not create a lawyer-client relationship.


Sources

[1] Telecommunications Business Act B.E. 2544 (2001)

[2] NBTC rights-of-way notification published 16 February 2017

[3] Government citizen guide for section 39 applications

[4] NBTC communications-duct guidelines published 2 June 2017

[5] Department of Highways citizen guide for utility works

[6] PEA communications-cable attachment regulations B.E. 2566 (2023)

[7] PEA announcement on removal of unauthorized cables

[8] Highway Act B.E. 2535 (1992) consolidated Thai text

[9] MEA communications-cable attachment regulation B.E. 2566 (2023)


Authors

  • Naytiwut Jamallsawat

    Naytiwut Jamallsawat is a partner at Formichella & Sritawat and heads the firm’s Corporate and Regulatory practice. He advises multinational and Thai clients on complex regulatory and transactional matters, with particular emphasis on telecommunications, satellite services, media, data privacy, cybersecurity, energy, and foreign investment. His work includes market-entry structuring, licensing and regulatory compliance, regulated transactions, and conventional and renewable energy projects.
    Naytiwut is ranked Band 2 for TMT by Chambers Asia-Pacific and a Leading Partner for TMT by The Legal 500. He holds an LL.B. from Chulalongkorn University and LL.M. degrees from the University of Kent and the University of Dundee.

  • Onnicha Khongthon

    Onnicha Khongthon is a senior associate at Formichella & Sritawat with more than seven years of experience across telecommunications, media, and technology, data privacy, cybersecurity, satellite and space law, and corporate and commercial matters. She advises Thai and international businesses on telecommunications licensing, commercial agreements, regulatory compliance, and market entry, including BOI promotion, Treaty of Amity structures, and foreign business approvals.
    Onnicha has contributed to leading international publications on telecommunications, digital business, and technology transactions, as well as the World Bank Group’s Women, Business and the Law research. She holds an LL.B. from Chulalongkorn University.

  • Supitchaya Akeyati

    Supitchaya Akeyati is an associate at Formichella & Sritawat whose practice focuses on data privacy, telecommunications, media, and technology, corporate and commercial law, regulatory licensing, and foreign investment. She works with Thai and international clients on PDPA compliance, cross-border data governance, corporate matters, and regulatory issues affecting digital businesses and communications providers.
    Supitchaya has contributed to Thailand chapters published by Chambers and Partners and the International Comparative Legal Guides, covering technology transactions, digital business, data protection, and telecommunications and media regulation. She holds an LL.B. from the Faculty of Law at Prince of Songkla University.